DURATION
48 hours
Due to a serious rear-end collision on 28/08/2023, a dangerous goods transporter loaded with high-pressure tanks exploded. The collision quickly led to a fire which spread to several vehicles. This caused severe damage to the concrete carriageway.
The A2 is considered an important east-west link between Hanover and Berlin, meaning that the fastest possible repair was necessary to avoid long periods of closure
The blaze causes sever damage to around 400 square metres of motorway
Two excavators working in parallel to remove the damaged concrete slab gently
Cutting of the concrete surface into manageable pieces using two powerful cutting machines
Load of a concrete section
Use of mobile concrete mixers with a mixing capacity of 0.75 m³/min (3 mixers were operated in rotation to ensure an uninterrupted concrete supply)
Due to the rapid drying of the quick-set concrete, the surface must be smoothed and textured with a broom coat immediately after pouring the concrete